Furnace renovation: example of a 4 working days project

Furnace renovation: example of a 4 working days project. The photo’s show :
Removing the damaged lintel (left) and mounting of a new lintel girder (right)
Arrival and mounting of a new furnace door frame
Mounting of fast exchangeable prefab lintel blocks (mounting time per block 15 min.) and day 4: finished.